Figure 85: Remove Battery Cover
c. Slide the battery cartridge connector through the hole in the battery cover and
set the battery cover aside.
d. Slide the battery cartridge out of the UPS.
e. Slide the new battery cartridge into the UPS.
f. Slide the new battery cartridge connector through the hole in the battery cover.
g. Replace and secure the battery cover (reverse order of above).
h. Connect the new battery cartridge to the UPS. Press connector tightly together
to ensure a proper connection.
i. Replace the UPS faceplate.
5. If EBP units are part of the system, perform the EBP Battery Cartridge replacements
on all the EBP units in the system before changing the UPS back to the Normal state.
6. Change the UPS in the system back to the Normal state.
7. Allow time for the UPS to transitions to the Normal state (about 30 seconds).
8.
Note:
If adding or removing EBP units to the system at the same time, appropriately
adjust battery capacity on the system in the UPS (see SmartZone UPS 1-3kVA User
Manual
– Setup Operation – Double Conversion VRLA UPS – Screen 4) before
running the manual battery test.
9. Manually run a battery test to ensure the full capacity battery is connected.
EBP Battery Cartridge Sets for the 1-3kVA UPS Systems
(UVD024, UVD036, UVD048, UVD072)
Replace battery cartridges with only the same SKU. It is recommended to replace all
battery cartridges in a system at the same time with new battery cartridges of the same
SKU for that unit (EBP).
1. The UPS should still be in the Bypass state from the above steps.
2. The breaker on the back of each EBP unit should be off from the above steps.
3. Perform the following steps on each EBP in the system.
a. Remove the faceplate by pressing on both sides of EBP faceplate until the
latches release and remove (see figure below).