SMARTZONE UPS INSTALLATION MANUAL
11
Section 3
– UPS, EBP and MBS Mounting
The UPS, EBP and the MBS have different mounting options. Refer to the following
section that matches the desired mounting technique desired.
Racks
Four-post rack mounting is the recommended preferred mounting technique for all UPS,
EBP and MBS units. The mounting hardware for this technique is provided with most
units. The units may also be mounted in a two-post rack, this will require additional
mounting hardware that is specified in the below section. (
Note:
It is recommended to
mount the UPS and EBP unit near the bottom of the rack due to the physical weight of
these units). The third mounting option is tower mounting. This is not the preferred
mounting technique, but tower mounting stands are provided with most units. The 3-
Phase UPS and EBP unit should not use this mounting technique due to physical
configuration and physical weight of the unit.
Four-Post Racks
The UPS, EBP and MBS units come with the hardware required for installation in a
standard EIA or JIS seismic rated four-post rack with square or M5 threaded mounting
holes. The rail assemblies adjust to mount in 19” racks with a front to rear distance of
460~1000 mm (18 to 39 inches).
CAUTION
⚫
The unit is heavy. Removing the unit from its carton requires a
minimum of two people.
⚫
If installing optional EBP(s), make sure to install the EBP(s)
directly below the UPS so the wiring between the units can use
the wiring provided with the units.
Note:
Mounting rails are required for each individual unit.
Install 2U UPS Units (U01N11L, U01N11V, U01S11L, U01S11V, U01N12L, U01N12V,
U01S12L, U01S12V, U01N13V, U01S13V, U02N11L, U02N11V, U02S11L, U02S11V,
U02N12L, U02N12V, U02S12L, U02S12V, U03N11L, U03N11V, U03S11L, U03S11V,
U03N12L, U03N12V, U03S12L, U03S12V)
1. Install the URMKIT2 rail kit:
a. Install the front side of the rail kit with 3x Phillips Pan Head M5 screws (see
figure below) on each rail. Do not tighten the screws.