SMARTZONE UPS INSTALLATION MANUAL
16
Figure 9: Secure the Mounting Brackets to the Rack
Install 2U EBP Units (UVP024, UVP036, UVP048, UVP072)
It is recommended to install the first EBP unit directly under the UPS unit. It is
recommended to install all subsequent EBP units directly under the previous EBP unit.
1. Install the URMKIT2 rail kit:
a. Install the front side of the rail kit with 3x Phillips Pan Head M5 screws (see
figure below) on each rail. Do not tighten the screws.
Figure 10: Install the Front Side of Rails
b. Adjust the rail size according to the depth of the rack