PACD011001G2 / PACD011004G3
Installation 2
Urban Multi Inverter “MX1” Series
65
4.2.4
Test Run Adjustment
Procedure and essential points
The order of the test run operations is extremely important and they should be carried out in accordance
with the following principles:
1. Checks to be carried out before switching the power on.
2. Switch on the main power supply
Miscellaneous checks :
l
Assembly of indoor and outdoor units
l
Presence or absence of trap on gas pipe side
l
Pipe size
l
Presence or absence of thermal insulation
(It is assumed that the vacuum drying operation has been completed.)
Check for incorrectly laid power cables
and loose screws.
Check for incorrectly laid control
cables and loose screws.
Additional charge of refrigerant when
length of refrigerant piping exceeds
10m.
Open gas line stop valve to the full.
Open liquid line stop valve to the full.
Measure insulation.
l
Use a 500V insulation tester.
l
Do not use a insulation tester between indoor and
outdoor units or between indoor unit and remote
controller. (Because they are low voltage circuit)
(M120)
Switch on the outdoor units.
Switch on 6 hours before the system
starts operating (To energize the crank
case heater).
Set each of the setting switches for
various modes.
Switch on the indoor units.
(M011)
Содержание Urban Multi MX1 Series
Страница 34: ...Installation 1 PACD011001G2 PACD011004G3 34 Urban Multi Inverter MX1 Series Ceiling Type CS TM ...
Страница 54: ...Installation 1 PACD011001G2 PACD011004G3 54 Urban Multi Inverter MX1 Series ...
Страница 102: ...Appendix Check Points in Installing UM Series PACD011001G2 PACD011004G3 102 Urban Multi Inverter MX1 Series ...
Страница 103: ...PACD011001G2 PACD011004G3 Appendix Check Points in Installing UM Series Urban Multi Inverter MX1 Series 103 1 ...
Страница 104: ...Appendix Check Points in Installing UM Series PACD011001G2 PACD011004G3 104 Urban Multi Inverter MX1 Series ...