RGPS Cabling for Multi–BTS Configurations Equipped with Optional
Primary Surge Suppressor
– continued
DEC 2000
5-33
SC
t
300 BTS Hardware Installation, ATP and FRU Procedures
PRELIMINARY
Cable Diagram
Figure 5-25 and Figure 5-26 both show the cabling for multi–unit
configurations for both RGPS (sychronous) and HSO
(non–synchronous).
Procedure
Connect the cables (Cable X) between the Primary Surge Suppressors of
each BTS. Refer to the cable run list in Table 5-19, Figure 5-25, and
Figure 5-26.
5