Site I/O, Span Line, RGPS and Modem Cabling for Sites Equipped With
Primary Surge Suppressor
– continued
DEC 2000
5-25
SC
t
300 BTS Hardware Installation, ATP and FRU Procedures
PRELIMINARY
Procedure to Install Site I/O
Cable Between Site I/O
Junction Box and Optional
Primary Surge Suppressor
Do the procedure in Table 5-13 to connect the Site I/O cable. Refer to
Figure 5-22, Figure 5-23 and Figure 5-24.
Table 5-13: Procedure to Install Site I/O Cable Between Site I/O
Junction Box and Optional Primary Surge Suppressor
Step
Action
1
Route the Site I/O cable(s) from the unit location to the
Primary Surge Suppressor.
2
Connect the Site I/O cable from unit 1 to the connector
labeled SITE I/O 1 on the right side of the Surge Suppressor.
3
Connect the appropriate conductors or wires to the Primary
Surge Suppressor Punchdown block.
Figure 5-22: Site I/O Cabling Details with Optional Primary Surge Suppressor (MicroCell Unit Shown)
PRIMARY
SURGE
SUPPRESSOR
SITE I/O
JUNCTION BOX
SITE I/O
CABLE
AC
POWER
T
ANTENNA
D
MASTER
GROUND
Y
MICROCELL 1
CUSTOMER
INPUTS
SPAN
RGPS
PHONE
(MODEM)
M
N
O
V
SITE I/O
INTERFACE
CONDUIT
5