Carrier and septum purge lines extended with unions and PEEK tubing
The stainless steel tubing for the carrier supply line is 1/16” while the septum purge line is 2mm and will
require a different ferrule when connected to the 1/8” brass union.
NOTE
: two 1/8” brass unions, 3 m of 1/16” green PEEK tubing and 1/8” graphitized vespel ferrules,
including one for 2 mm tubing, are all contained within the UNITY–Air Server-xr shipping kit.)
Connect the carrier gas supply line to the ‘Carrier Inlet’ port of UNITY–Air Server-xr and connect the
septum purge line to the ‘Pressure Outlet’ port.
6.2.2
7890 Inlet Setup
There are several settings that must be implemented on the 7890 whenever the split/splitless EPC
module is controlling the carrier gas supply to the UNITY-xr thermal desorber. In the Inlet settings the
mode must be set to ‘Splitless’, the purge time must be set to exactly ‘999.99’ minutes and Gas saver
should be set to ‘Off’. In the Instrument Configuration menu the Auto prep run should be set to ‘Off’.
Having completed this, the system should now be ready to use.
6.2.3
7890 Inlet Settings
If the pressure is not correctly controlled after inputting the above settings then turn ‘Auto prep run’ to
‘On’.