Final checks
After the installation, adjustment and programming is completed and the lift display shows
no errors during testing of all lift functions please check again the following.
Make the following checks before handing over the unit to the client:
Check all fastenings of the rail to the wall/pillars and pillars to the steps
Check connections of rail parts for strength and proper alignment
Check proper fastening of the motor box
Ensure that the rope is tensioned properly. If it is too loose, it may short against the
tube.
The current donator and current collector system must be correctly connected to the
control boards
Check clearance of the platform to the steps and opposite walls under full load
Check function of directional safety switches: safety bottom under pan, loading
ramps, landing stop limit switches
Check ultimate limit switches function
Check barrier arm safety switch function
Check proper platform position at lower stop under full load; make sure safety bottom
is not pressed before lower stop limit switch is pressed and check proper alignment
of loading ramps
Check barrier arms for horizontal alignment
Check all platform functions: Drive up and down with handset (open platform) and
hall calls (closed platform), opening and closing of platform in landing stations.
Check key switch and stop button operation
Check proper fixing and position of all platform covers
If you encounter any problems, please refer to the detailed electrical and technical
documentation in the attachment.