Installation
XHD Installation, Operation, and Maintenance Manual
33
5. Allow the grout to set.
Item Description
1.
Baseplate
2.
Shims or wedges
3.
Grout
4.
Foundation
5.
Sleeve
6.
Dam
7.
Bolt
Figure 23: Pour grout into baseplate
6. Fill the remainder of the baseplate with grout, and allow the grout to set for at least 48
hours.
Item Description
1.
Baseplate
2.
Grout
3.
Foundation
4.
Dam
5.
Bolt
Figure 24: Fill remainder of baseplate with grout
7. Tighten the foundation bolts.
8. Recheck the alignment.
Piping checklists
General piping checklist
Precautions
WARNING:
• Risk of premature failure. Casing deformation can result in misalignment and contact with
rotating parts, causing excess heat generation and sparks. Flange loads from the piping
system, including those from the thermal expansion of the piping, must not exceed the
limits of the pump.
Содержание Goulds Pumps XHD
Страница 1: ...Installation Operation and Maintenance Manual XHD ...
Страница 2: ......
Страница 27: ...Installation XHD Installation Operation and Maintenance Manual 25 Direct coupled baseplate leveling worksheet ...
Страница 147: ...Parts Listings and Cross Sectionals XHD Installation Operation and Maintenance Manual 145 Figure 130 Optional features ...
Страница 151: ...Parts Listings and Cross Sectionals XHD Installation Operation and Maintenance Manual 149 ...
Страница 153: ...Certification CE or CE ATEX XHD Installation Operation and Maintenance Manual 151 ...
Страница 154: ...Certification CE or CE ATEX XHD Installation Operation and Maintenance Manual 152 ATEX notification ...
Страница 155: ...Certification CE or CE ATEX XHD Installation Operation and Maintenance Manual 153 IECEx Certificate of Conformity ...
Страница 156: ...Certification CE or CE ATEX XHD Installation Operation and Maintenance Manual 154 ...
Страница 157: ...Certification CE or CE ATEX XHD Installation Operation and Maintenance Manual 155 Chinese Certificate of Conformity ...