Figure 3-76
Assembling the OT bare crimp terminal to the DC power cable
L
L1
L2
1
2
3
----End
Follow-up Procedure
Verify the following after the connection is complete:
l
The power cables are correctly and firmly connected to the power supply device.
l
If multiple USGs are deployed, the power cables of each USG are correctly labeled for
distinction.
3.5.9 Powering On or Off the USG6650/6660/6670/6680
This section describes how to power on or off the USG6650/6660/6670/6680. To ensure the
normal start and security of the USG6650/6660/6670/6680, strictly follow the operation guide
to power on or off the USG6650/6660/6670/6680.
Context
Before you power on the USG, ensure that:
l
The power cable and PGND cable are properly connected.
l
The power switch in the equipment room is easy to locate so that you can power off
devices in the case of accidents.
Procedure
l
Power on the USG.
Turn on the switch of the power supply device and then the switch on the power module
of the USG. The USG starts.
You can identify the USG status based on indicators on the SPUA panel. Indicators
shown in
indicate that the USG runs normally.
HUAWEI USG6000 Series
Hardware Guide
3 Hardware Installation
Issue 08 (2017-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
333