Figure 3-53
Connecting AC power cables
Secospace USG6000
4 HDD
5 PWR 6 PWR
INPUT OUTPUT
ON
OFF
~100-240V;50/60Hz;2.5A
XXXXXXXXXXXXXXXXXXXXXXXXXXX
SM-HDD-SAS300G-B
AC power cable
AC power supply
2
1
INPUT OUTPUT
ON
OFF ~100-240V;50/60Hz;2.5A
3
----End
Follow-up Procedure
Verify the following after the connection is complete:
l
The power cable is firmly connected to the power supply socket.
l
If multiple USGs are deployed, the power cables of each USG are correctly labeled for
distinction.
3.4.9 Powering On or Off the
USG6306/6308/6330/6350/6360/6370/6380/6390/6390E/
6507/6530/6550/6570/6620/6630
This section describes how to power on or off the
USG6306/6308/6330/6350/6360/6370/6380/6390/6390E/6507/6530/6550/6570/6620/6630.
To ensure the normal start and security of the
USG6306/6308/6330/6350/6360/6370/6380/6390/6390E/6507/6530/6550/6570/6620/6630,
strictly follow the operation guide to power on or off the
USG6306/6308/6330/6350/6360/6370/6380/6390/6390E/6507/6530/6550/6570/6620/6630.
Context
Before you power on the USG, ensure that:
l
The power cable and PGND cable are properly connected.
HUAWEI USG6000 Series
Hardware Guide
3 Hardware Installation
Issue 08 (2017-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
305