3.14 Verifying the Installation
Table 3-9 Check items
Item
Check That
Check Result
Refrigerant
pipe
Ports are connected properly. The pipeline
has oil traps, gradients (for the refrigerant
pipes), and pipe supports. Pipes are
securely connected. All pipes and stop
valves are wrapped with thermal
insulation foam, and the insulation foam
is intact. The needle valve plug is secured
(torque of 0.45±0.05 N·m), and the valve
bonnet is tightened. The pipes have no
sharp bends.
□ Passed. □ Failed
Waterway
Water pipe joints have been sealed. The
drainpipe is securely connected.
□ Passed. □ Failed
Electricity
The power cables and signal cables are
connected as required. Indoor and
outdoor units are properly grounded.
Cables are not damaged or over-bent. The
rated specifications of the upstream
switch meet the maximum current
requirement.
□ Passed. □ Failed
Cabinet
The cabinet is installed properly, without
any tilt. The cabinet is secured. The
foreign matter inside the cabinet such as
cable ties and cable cuts is cleaned up.
□ Passed. □ Failed
Wet film
humidifier
The humidifier water inlet pipe is properly
connected and secured.
□ Passed. □ Failed
Water pan
The foreign matter inside the water pan is
cleaned up.
□ Passed. □ Failed
Air filter
The air filters have been installed.
□ Passed. □ Failed
Fan
The fan is secured. The fan has no foreign
matter inside.
□ Passed. □ Failed
Outdoor unit The fan blades do not interfere. Cables
are protected by tubes and the cable
outlet faces downward. The protective
cardboard of condenser fin has been
removed.
□ Passed. □ Failed