9 Commissioning Core Components
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
79
For the setting method, see the UPS2000-G user manual.
UPS2000-Gs can work in single or parallel mode. Check the initial configurations against
the single or parallel initial configuration table based on the actual situation.
You are recommended to
Language
to the local language after all settings are completed.
Step 4
After verifying that the initial configurations are correct, switch on the UPS2000-G output
circuit breakers.
----End
9.2 Commissioning Cooling Components
9.2.1 Commissioning Chillers
Prerequisites
The chiller has been powered on.
Preparations
Tools: step ladder, clamp meter
Documents: documents delivered with the chiller, power supply and distribution system
diagram, cooling device layout diagram, chiller initial configuration table
Skill requirement: cooling engineer
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Start the chiller pumps on the controller in the electric control box of chiller 1. For details, see
the delivered chiller documents.
Step 2
Check whether the controller displays any alarms.
If an alarm is displayed, clear the alarm by following instructions in documents delivered with
the chiller before continuing the commissioning.
Step 3
Verify the initial configurations of the chiller by referring to the chiller initial configuration
table.