4 Preparations for Power-On Commissioning
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
21
To ensure the normal running of the cooling system, check that the pressure of the automatic
water refill valves stays greater than 0.15 MPa. If the cooling system is put into use right after
the secondary refrigerant is filled, you do not need to shut down the auxiliary water refill
devices.
----End
4.5.7 Expelling Air from the Cooling System
4.5.7.1 Expelling Air from the Expansion Tanks
Prerequisites
The auxiliary water refill devices keep filling secondary refrigerant to the system.
Preparations
Tool: step ladder
Documents: pipe system diagram, pipe system valve control relationship table
Skill requirement: cooling engineer
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Open the overhaul valve for an expansion tank, as shown in