FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
7 System Commissioning
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
44
7
System Commissioning
7.1 Power Supply and Distribution System
Commissioning
Before putting the FusionModule1000 into use, you must commission the power supply and
distribution system to ensure normal power supply.
7.1.1 Verifying the Switchover Between Two Power Supplies
Prerequisites
The FusionModule1000 is powered on, commissioned, and working properly.
Devices that have two power supplies have been properly powered on by both supplies.
This section describes how to perform the switchover for a device that has two power supplies, using the
RH2288 server as an example.
Preparations
Tools: none
Documents: power supply and distribution system diagrams, monitoring device layout
Skill requirement: power distribution system engineer
For the diagram, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Remove one power plug for the RH2288 server or switch off the corresponding rPDU input
circuit breaker in the PDC.
Step 2
Power on the RH2288 server 30s later. Check that the server works properly.
Step 3
Remove the other power plug for the RH2288 server or switch off the corresponding rPDU
input circuit breaker in the PDC.
Step 4
Power on the RH2288 server 30s later. Check that the server works properly.