FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
7 System Commissioning
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
52
Figure 7-8
Short-circuiting the pressure announciator terminals
(1) Red and black cables to the pressure
announciator
(2) Cables to the fire alarm control
panel
Step 9
Commission the emergency start/abort switch.
The panel of the emergency start/abort switch is for one-time use only. Before the
commissioning, remove the panel to operate the emergency start/abort switch directly, as
shown in
Reset the START and STOP buttons after the commissioning (the buttons bounce up).
Figure 7-9
Emergency start/abort switch