FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
9 Commissioning Core Components
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
97
9.4 Commissioning Fire Extinguishing Devices (Standard)
9.4.1 Commissioning the Fire Alarm Control Panel (standard)
Prerequisites
Initial configuration parameters have been set for the fire alarm control panel before delivery
and do not need to be set onsite.
Preparations
Tools: none
Documents required: power supply and distribution system diagram, documents delivered
with the agent releasing control panel, fire extinguishing system conceptual diagram
(standard), fire extinguishing device layout diagram (standard)
Skill requirement: fire engineer
For the diagrams, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Switch on the input power circuit breaker of the fire alarm control panel for the protected area
by referring to the power supply and distribution system diagram.
Step 2
Switch on the active and standby power supply to power on the fire alarm control panel.
Figure 9-13
Positions of power switches
If the power indicator is on and other indicators are off, the power-on process succeeds. If a
yellow fault indicator is on, rectify the fault before continuing follow-up operations.