FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
9 Commissioning Core Components
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
78
9.1.3 (Optional) Commissioning the UPS2000-G
Prerequisites
The upstream PDC of the UPS2000-G has been powered on.
Battery packs or batteries have been installed and connected, and the installation has
been verified.
Preparations
Tool: Phillips screwdriver
Documents: documents delivered with the UPS2000-G, power supply and distribution system
diagram, power supply and distribution component layout, UPS2000-G single system initial
configuration table, UPS2000-G parallel system initial configuration table
Skill requirement: power distribution system engineer
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Switch on the input power circuit breaker of the UPS2000-G to power on the UPS2000-G.
If the output circuit breaker cannot be switched on within 5 minutes after the UPS2000-G
input power circuit breaker has been switched on, disconnect the input power circuit breaker.
Otherwise, the UPS2000-G will enter the protection mode automatically.
Step 2
Start the UPS2000-G and verify the initial configurations.
If an alarm is generated after the power-on, rectify the fault before continuing the
power-on commissioning.
During the power-on commissioning, you are not allowed to switch on the bypass circuit
breaker for the UPS2000-G.
During the UPS2000-G power-on commissioning, you are not allowed to modify the
UPS2000-G initial configurations unless you are authorized by onsite Huawei engineers.
Step 3
Enter the user name and password to enter the operation screen, and verify that initial
parameter settings are consistent with the initial configuration table.