FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
4 Preparations for Power-On Commissioning
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
17
Figure 4-2
Closing the overhaul valve for the automatic water refill valve
Step 2
Start the auxiliary water refill device to supply water to the automatic water refill valve, and
check whether the value displayed on the barometer of the automatic water refill valve is 0.15
MPa.
If the pressure reading is 0.15 MPa, open the service valve for the automatic water refill
valve.
If the pressure reading is not 0.15 MPa, go to
automatic water refill valve.
Step 3
Loosen the lock nut, and rotate the adjustment bolt counterclockwise to fully loosen it, as
shown in
. Slowly rotate the adjustment bolt clockwise until the pressure reads 0.15
MPa. Then tighten the lock nut.