Chapter 3 Installation
3.1 Open the packages and Check
After receive the cargo, please open and check the items. If the cargo is not right, please contact
Honeybee Sales or Dealer.
3.2 Portable CNC Cutting Machine Installation
(The example is HBST2008LCD and Thermadyne Cutmaster A120 plasma power
source).)
3.2.1 Longitudinal Rails Assembly (Y Axis)
Take the frame constituted by the two longitudinal rails
Take the two transversal beams
Slide the captive nuts to the place where one transversal beam will be install on the frame (
≈
400mm from
the edge of the frame) See picture 3.
Put one transversal beam in place, insert 4 M8 screws through the beam into the captive nuts and torque
them. See picture 4.
Picture 2:Transversal beam screw Picture 3: Longitudinal Rails Frame Assembled
3.2.2 Central Unit Installation
—Hold the Central Unit Front Panel and make the guiding blocks fit well with the two rails.
—Put the guiding blocks on the rails carefully.
M8 Captive nut
rails
Base
frame
M8