1-14
C60 Breaker Protection System
GE Multilin
1.3 ENERVISTA UR SETUP SOFTWARE
1 GETTING STARTED
1
1.3.5 CONNECTING TO THE C60 RELAY
When unable to connect because of an "ACCESS VIOLATION," access
Device Setup
and refresh the order code for the
device.
1.
Open the Display Properties window through the Site List tree as shown. The Display Properties window opens with a
status indicator on the lower left of the EnerVista UR Setup window.
2.
If the status indicator is red, verify that the Ethernet network cable is properly connected to the Ethernet port on the
back of the relay and that the relay has been properly setup for communications (steps A and B earlier).
If a relay icon appears in place of the status indicator, than a report (such as an oscillography or event record) is open.
Close the report to re-display the green status indicator.
3.
The Display Properties settings can now be edited, printed, or changed.
See chapter 4 in this manual or the EnerVista UR Setup Help File for information about the using the EnerVista UR
Setup software interface.
QUICK ACTION HOT LINKS
The EnerVista UR Setup software has several quick action buttons to provide instant access to several functions that are
often performed when using C60 relays. From the online window, users can select the relay to interrogate from a pull-down
window, then click the button for the action they want to perform. The following quick action functions are available:
•
View the C60 event record
•
View the last recorded oscillography record
•
View the status of all C60 inputs and outputs
•
View all of the C60 metering values
•
View the C60 protection summary
•
Generate a service report
842743A3.CDR
Communications status indicators:
Green = OK
Red = No communications
UR icon = report is open
Quick action hot links
Expand the site list by double-clicking
or selecting the +/– box.
NOTE
Содержание C60
Страница 10: ...x C60 Breaker Protection System GE Multilin TABLE OF CONTENTS ...
Страница 30: ...1 20 C60 Breaker Protection System GE Multilin 1 5 USING THE RELAY 1 GETTING STARTED 1 ...
Страница 420: ...5 284 C60 Breaker Protection System GE Multilin 5 10 TESTING 5 SETTINGS 5 ...
Страница 423: ...GE Multilin C60 Breaker Protection System 6 3 6 ACTUAL VALUES 6 1 OVERVIEW 6 FIRMWARE REVISIONS See page 6 28 ...
Страница 466: ...8 4 C60 Breaker Protection System GE Multilin 8 1 FAULT LOCATOR 8 THEORY OF OPERATION 8 ...
Страница 478: ...9 12 C60 Breaker Protection System GE Multilin 9 6 DISPOSAL 9 MAINTENANCE 9 ...
Страница 492: ...A 14 C60 Breaker Protection System GE Multilin A 1 PARAMETER LISTS APPENDIX A A ...
Страница 648: ...E 10 C60 Breaker Protection System GE Multilin E 1 OVERVIEW APPENDIX E E ...
Страница 660: ...F 12 C60 Breaker Protection System GE Multilin F 2 DNP POINT LISTS APPENDIX F F ...
Страница 670: ...H 8 C60 Breaker Protection System GE Multilin H 2 ABBREVIATIONS APPENDIX H H Z Impedance Zone ...
Страница 672: ...H 10 C60 Breaker Protection System GE Multilin H 3 WARRANTY APPENDIX H H ...
Страница 682: ...x C60 Breaker Protection System GE Multilin INDEX ...