Power Xpert
9395 UPS (450–550 kVA) Installation and Operation Manual
164201701 Rev 3
www.eaton.com/powerquality
3-1
Chapter 3
UPS Installation Plan and Unpacking
Use the following basic sequence of steps to install the UPS:
1.
Create an installation plan for the UPS system (Chapter 3).
2.
Prepare your site for the UPS system (Chapter 3).
3.
Inspect and unpack the UPS cabinet (Chapter 3).
4.
Unload and install the UPS cabinet, and wire the system (Chapter 4).
5.
Install features, accessories, or options, as applicable (Chapter 5).
6.
Complete the Installation Checklist (Chapter 4).
7.
Have authorized service personnel perform preliminary operational checks and
startup.
NOTE
Startup and operational checks must be performed by an authorized Eaton Customer Service
Engineer, or the warranty terms specified on page W-1 become void. This service is offered as part of the
sales contract for the UPS. Contact an Eaton service representative in advance (usually a two-week notice is
required) to reserve a preferred startup date.
3.1
Creating an Installation Plan
Before installing the UPS system, read and understand how this manual applies to the
system being installed. Use the procedures and illustrations in paragraph 3.2 and
Chapter 4 to create a logical plan for installing the system.
3.2
Preparing the Site
For the UPS system to operate at peak efficiency, the installation site should meet
the environmental parameters outlined in this manual. If the UPS is to be operated at
an altitude higher than 1500m (5000 ft), contact an Eaton service representative for
important information about high altitude operation. The operating environment must
meet the weight, clearance, and environmental requirements specified.
3.2.1
Environmental and Installation Considerations
The UPS system installation must meet the following guidelines:
The system must be installed on a level floor suitable for computer or electronic
equipment.
The system must be installed in a temperature and humidity controlled indoor area
free of conductive contaminants.
The cabinet can be installed in
line‐up‐and‐match
or
standalone
configurations.
Failure to follow guidelines may void your warranty.
The UPS equipment operating environment must meet the weight requirements
shown in Table 3‐1 and the size requirements shown in Figure 3‐1 through Figure 3‐7.
Dimensions are in millimeters (inches).
Figure
Содержание Power Xpert Plus 1
Страница 1: ...Power Xpert 9395 UPS and Plus 1 UPS 450 550 kVA Installation and Operation Manual...
Страница 193: ......
Страница 194: ...1642017013 164201701 3...