Cycling the System
1. Check that you have correctly performed the
following:
a. Installed the stack in the thruster and have closed
the stack access cover securely.
b. Secured the fixture in place.
c. Performed the Operational Test of the Acoustic
Stack as detailed on Page 116 of this section.
2. Verify that all controls on the Press/Thruster and the
generator are set as required for this operation.
3. Place a part in the fixture.
4. Manually cycle the system.
Activate both operate switches at the same time to
start the system, and hold fingers in place until the
ultrasound starts. Releasing the fingers before ultra-
sound starts will abort the cycle.
Page 119
Dukane Manual Part No. 403-587-00
Section 7 - System Operational Testing
Содержание ES
Страница 127: ...SECTION 8 Maintenance Page 121 Dukane Manual Part No 403 587 00 Section 8 Maintenance ...
Страница 137: ...SECTION 10 Contacting Dukane Page 131 Dukane Manual Part No 403 587 00 Section 10 Contacting Dukane ...
Страница 171: ...Index Page 165 Dukane Manual Part No 403 587 00 Index ...