30
LP Panelized Baghouse 684LP - 882LP
4. Move the completed first body panel ring assembly (with hand-tightened hardware) off the tubesheet onto a level area using
standoffs to avoid ground contact.
Note: Lifting points bolt-on usage - use the provided bolt-on lifting points and grade 5 hardware when moving panels into
position. Position the lugs such that excess swaying will be minimized. When lifting an assembly, use all four lugs
with the backer plates attached.
5. Repeat Steps 1-4 for all rings of the dirty-air plenum (BS3, BS2 and BS1).
6. Apply sealant to the top flange of each body panel ring. See Detail B on Dirty-Air Plenum Assembly illustration.
7. Properly attach the lifting points with the Grade 5 hardware to each assembled ring. Lift the second ring (BS3) and set on top
of the first ring (BS4). Lift third (BS2) and set on second (BS3) and lift the fourth (BS1) and set onto third (BS2).
Note: Vertical seams on each section must be spaced apart by a minimum of 4 bolt spaces. See Detail A on Dirty-Air Plenum
Assembly illustration.
8. Tighten all hardware per the hardware table found in Tubesheet Assembly.
9. Set the completed dirty-air plenum assembly off to the side. Use standoffs under the flanges to keep them off grade.