LP Panelized Baghouse 684LP - 882LP
14. Additional Ducting
After collector is completely erected the rest of the ducting may be connected. It is important to ensure that the ducting is
adequately supported and that the weight is not entirely on the collector.
15. Material Discharge Mechanism
The material discharge device flange should be prepared with sealant to ensure an air tight seal. Lift the device into position and
bolt into place. Depending on the accessory, additional support may be required.
16. Electrical Connections
All electrical connections are the responsibility of the process owner. Follow all local and national electrical codes when installing
service. Any wiring on the interior of the collector may need to be rated for explosive environments. Consult your local codes.
17. Fire Mitigation System
Consult with local authorities when installing fire control systems on dust collection equipment.
Sprinkler couplings are provided for the convenience of fire control system installers. The fire control system installer shall make
their own decisions on the appropriate location of fire control system components.
18. Structural Connections
Before placing collector into service it is important that all structural connections be inspected for proper torque. It is recommended
that all structural bolts be checked and re-tightened if necessary.
19. Electrical and Mechanical Connections
Before placing collector into service it is important that all electrical connections are inspected and approved.