LP Panelized Baghouse 684LP - 882LP
LP General Assembly Sequence Overview
Electrical installation must be performed by a qualified electrician.
Duct fabrication and installation must be performed by a qualified tinsmith or contractor.
This equipment is not designed to support site ducts, piping, or electrical services. All ducts, piping, or electrical
services must be adequately supported to prevent injury and/or property damage.
The following steps summarize the order in which to assemble the collector. Depending on the process owner's situation a
different sequence may be more appropriate. Each of the following steps is explained in detail on the following pages. Read the full
installation instructions for clarification and important details before beginning assembly.
1.
Leg Assembly - assemble legs, cross bracing and I-Beam frame
2.
Tubesheet Assembly - this step is critical because all other sections will be aligned and assembled on the tubesheet, using the
tubesheet as a template.
3.
Hopper Assembly - assemble, then invert and lift into place.
4.
Tangential Inlet Assembly - assemble the inlet which makes up the outside ring wall of the inlet deflector section and lift into
place.
5. Bag Section Assembly - assemble dirty-air plenum Bag Section panels to create each ring assembly and lift into place.
6. Clean-Air Access Plenum Assembly - assemble clean-air exhaust plenum and roof section and set aside on a level surface.
7. Clean-Air Outlet Plenum and Roof Installation - assemble roof together and onto clean-air outlet plenum.
8. Tubesheet Installation and Support Column - lift tubesheet and attaching upper support column.
9.
Lower Plenum Access Section Attachment and Internal Cleaning Assembly - attach the first ring assembly to tubesheet and
installing filter cleaning assembly.
10.
Filter Bag and Cage Installation - installation of filter bags and cages from the clean-air plenum.
11. Clean-Air Outlet Plenum and Roof Section Attachment - attach the exhaust plenum access and roof section to the Lower
Plenum Access section.
12. Exhaust Ducting - attach exhaust ducting to clean-air outlet plenum
13. Ladder/Platform Installation - mount the platform to the plenum access section and installing ladders.
14. Additional Ducting - connect of any remaining ducting to collector.
15. Material Discharge Mechanism - install onto collector hopper.
16. Electrical Connections - Process Owners are responsible for installation of electrical connections.
17.
Fire Mitigation Systems - Consult with local authorities when installing fire control systems on dust collection equipment.
18. Structural Connections - structural connections must be inspected for proper torque prior to commissioning the collector.
19.
Electrical and Mechanical Connections - before commissioning collector, all electrical and mechanical connections must be
inspected and approved.