2.2 INSTALLATION PROCESS
1.
Site the Smoke Screen, fix to the wall or ceiling as appropriate.
2. Make connections as required to the control system, i.e. Alarm Panel and Hold-off PIR.
3. Make connection to the Smoke Screen Interface (if used) and set the key switch to isolate.
4.
Connect and turn on the mains power.
5.
Turn on the internal battery back-up.
6. The Smoke Screen will heat up to operating temperature in approximately 20 minutes.
7. Make relevant programming settings and set smoke timing for the specified room size.
8.
Insert a Swift-Fit fluid reservoir.
9.
Make sure all tamper switches are closed.
10. If fitted set the Smoke Screen Interface key switch to ‘Ready’ and you are ready for test.
2.3 ACCESS
To access the PCB connections, programming panel and mounting holes (battery and fluid access is
covered in the relevant sections) remove the front cover by unscrewing the set screws on either side and
unhooking it from the top of the case; refitting is the reverse process. Installation cable entry is through the
serrated grommet on the left back of the case.
8
Содержание TITANIUM Ti100
Страница 1: ...TITANIUM Ti70 Ti100 Ti150 INSTALLATION AND OPERATION MANUAL VERSION 28 November 2019 ...
Страница 15: ...Titanium Generic Connection Schematic PCB v2 15 ...
Страница 37: ...8 2 INSTALLER NOTES 37 ...
Страница 39: ...39 ...