Step 9
If you use redundant power leads, terminate the return 2 lead to the positive RET2 terminal on the ONS 15454.
Terminate the negative 2 lead to the negative BAT2 terminal on the ONS 15454. Use oxidation-preventative
grease to keep connections noncorrosive.
The configured ONS 15454 shelf can work with a single power line since the ONS 15454 power
configuration offers redundancy. When using the 15454-FTA3 fan-tray, if the ONS15454 shelf is
powered by a single power line, the BAT-FAIL alarm appears, the fans run at a maximum speed,
and the system does not comply with NEBS GR-63 Issue 3 and GR-1089 Issue 4 and 5 requirements.
In order to meet the above mentioned NEBS requirements, the ONS 15454 shelf must be powered
by both the DC power lines.
Note
Step 10
Route the cables out below the power terminals using the plastic cable clamp, as shown in
ONS 15454 Power Terminals, on page 73
.
Step 11
Connect the return cables to earth ground at power supply side.
Step 12
Return to your originating procedure (NTP).
DLP-G19 Turn On and Verify Office Power
This task measures the power to verify correct power and returns for the ONS
15454 shelf.
Purpose
Voltmeter
Tools/Equipment
ETSI:
• Connect the office ground to chassis. For detailed instructions on grounding,
refer to the
Electrostatic Discharge and Grounding Guide for Cisco CPT and
.
•
DLP-G17 Connect Office Power to the ONS 15454 ETSI , on page 70
•
DLP-G18 Connect Office Power to the ONS 15454 ANSI, on page 71
Prerequisite Procedures
Required
Required/As Needed
Onsite
Onsite/Remote
None
Security Level
Do not apply power to the shelf until you complete all installation steps.
Caution
Procedure
Step 1
Using a voltmeter, verify the office battery and ground at the following points on the fuse and alarm panel:
a) To verify the power, place the black test lead of the voltmeter to the frame ground. Place the red test lead
on the A-side connection and verify that it is between –40.5 VDC and –57 VDC. Place the red test lead
on the B-side connection and verify that it is between –40.5 VDC and –57 VDC.
Cisco ONS 15454 Hardware Installation Guide
74
Installing the ONS 15454 M12 (ANSI and ETSI) Shelf
DLP-G19 Turn On and Verify Office Power
Содержание ONS 15454
Страница 2: ... 2019 Cisco Systems Inc All rights reserved ...
Страница 16: ...Cisco ONS 15454 Hardware Installation Guide xvi Contents ...
Страница 28: ...Cisco ONS 15454 Hardware Installation Guide xxviii Preface Preface ...
Страница 36: ...Cisco ONS 15454 Hardware Installation Guide 6 Overview Cisco ONS 15454 M6 Shelf ...
Страница 510: ...Cisco ONS 15454 Hardware Installation Guide 480 Hardware Specifications Dimensions ...