Installation
Additional cascade floor standing
Floor standing rack assembly
1. Position the additional lower beam
on the ground, next to the existing
cascade. Fit the lower brackets on
the lower beam using the supplied
M8 bolts, spring washers and nut.
2. Fit the additional lower beam and
the upper bracket with existing
vertical columns using the supplied
M8 bolts, spring washers and nut.
3. Preassembly (on the other side)
the vertical column with lower and
upper beam.
4. Fit the preassembled vertical
column with lower beam.
5. Fit the upper beam on the upper
brackets using the supplied M8
bolts, spring washers and nut.
Attention: once in the correct and
final position, the floor standing rack
has to be fixed on the ground.
Collector assembly
6. Place the flow water collectors in
the upper space.
7. Place the return water collectors
in the middle recess.Connect the
water lines using the supplied
DN100 gaskets, M16 bolts, spring
washers and nuts.
8. Place the gas collectors in the lower
recess. Connect the gas lines using
the supplied DN65 gaskets, M12
bolts, spring washers and nuts.
Boiler positioning
9. Move the boiler in front of the floor
standing rack.
Once connected the boiler with
dedicated connection kit, push the
four brakes to block it.