5.12.5
Connecting a UUT
When setting up for a new test and connecting any equipment to the power source,
proceed as follows:
1.
Always make sure the power source is turned OFF at the POWER switch when
making any wire connections.
2.
Check that the output of the equipment under test is
OFF
and that the load is not
still energized. This applies in particular to DC Mode when driving a load with input
capacitance or batteries.
3.
Connect one end of each load wire to the L/+ and N/- output terminals on the rear
panel.
4.
Check the polarity of the connections and connect the other end of the load wires to
the input terminals of the equipment under test.