Page
22
of
44
3DGence Material Management System | version 1 | 03.2022
Fig. 18 Example of routing the communication cable out of the top beam
7.
Install the front cover of the connection between the two devices. To do this, insert the upper part of the cover into
the notch in the upper housing of the device (marked with an arrow in red in the figure below). Then, at the bottom
of the device, fasten the cover with the screw from the set (highlighted in red in the figure below).
Fig. 19 Place where the front cover is inserted into the upper casing of the device
Fig. 20 Screwing place for the front cover
8.
Connect the devices to the power supply according to the preferred method.
9.
Set the main switches of both devices to the ON position.
10.
Start the device using the switch on the front panel
11.
After the device has started up, check that the system has correctly detected the additional column of chambers by
moving the screen to the right. When the screen is moved, a screen should appear with active chambers numbered
4, 5 and 6.
12.
Perform the first regeneration cycle of the desiccant cartridges for the newly installed chambers.
13.
Once the desiccant cartridge regeneration cycle is complete, install the material drawers and desiccant cartridges.