Appendix A - Replacement of Modules and Parts
Confidential and Proprietary Information of ZTE CORPORATION 191
Connect the connectors, and measure the cabinet top jumper for
the antenna feeder performance indexes by an antenna feeder
analyzer (SITE MASTER), and then make the waterproof treatment
to the waterproof bend and connectors.
Note:
In the process of making waterproof treatment to the connectors of the
antenna feeder system, make sure that:
Wrap it with waterproof tape, sealing tape and insulating tape in turn.
The jumper should be bent softly without too large angle, and generally, the
bend radius is over 15 times of the jumper radius.
Insulating tapes should be wrapped from the bottom to the top in case of
rainwater leaking.
vii.
Power on all the ETRM modules on the PSM module panel.
4.
Confirmation after replacement
i.
Observe the running status of the ETRM and the AEM. If the
indicator is normal, the replacement is basically successfully.
ii.
Make a test call to check whether the BS runs normally after the
replacement.
Tower Amplifier Replacement
1.
Tools
i.
Adjustable wrenches (2)
ii.
Paper knife
iii.
Sharp nose pliers
iv.
Multimeter
v.
Socket wrench
vi.
Tools for safely climbing
vii.
Lifting tools
2.
Preparation:
i.
Perform the fault observation and analysis and determine the
replacement is necessary.
ii.
Prepare a good spare part with the same type as that of the faulty
jumper.
iii.
Prepare a damp-proof bag and carton, as well as some labels for
identification.