5. Operation
Page 24
105466
– TW-31-E - V1.9 - 06.04.2021
5.
Operation
5.1 First commissioning
After applying the mains voltage the following can appear on the display
- 4 circulating bars, then briefly the firmware, then the time, or
- 4 blinking, horizontal bars
The time must be checked/set. See section 5.4.
For further operation the tank monitor must be parameterized according to the con-
ditions of your system.
Incorrectly set parameters can cause malfunctions of the tank monitor!
The correct parameterization of the tank monitor is described in section7. !
In order to be able to assign the file to the corresponding customer when the files
are later evaluated by Welba-KONSOFT, it is important to enter the customer and
tank number when installing the tank monitor.
See section 7.1.1
It is recommendable to record the setting values of the tank monitor after commis-
sioning or to archive them as KONSOFT files. This allows us to deliver a pre-pro-
grammed tank monitors in case of a spare part delivery.
When exchanging the tank monitor at the end customer's site only the actual value
correction has to be re-entered.
NOTICE
NOTICE