Vertiv™ XTE 601E Series Equipment Enclosures Description and Installation Manual
Proprietary and Confidential © 2022 Vertiv Group Corp.
37
6.11
Lifting the Enclosure
ALERT!
Do not lift the enclosure with batteries, rectifiers, or converters installed.
Procedure
1.
Ensure the front door is closed and latched.
2.
Inspect the lifting eyebolts and ensure eyebolts and roof are free of damage.
3.
Ensure that the four eyebolts on top of the enclosure have their sides oriented towards the center of the enclosure with no
exposed threads as shown in Figure 6.5.
4.
Install a clevis and shackle or a threaded shackle in each eyebolt at the top of the enclosure as shown in Figure 6.5.
5.
Insert all four (4) 8’ minimum lifting slings securely through all four clevises or shackles as shown in Figure 6.5.
6.
To prevent the enclosure from tipping when the pallet retaining bolts are removed, slowly take up the slack with the crane.
NOTE!
DO NOT tighten the slings so that the pallet lifts. The weight of the pallet will make it difficult to remove the bolts
from the pallet brackets.
NOTE!
It is important that the length of each sling allow for an angle 45
°
or more.
NOTE! Failure to maintain a 45
°
angle or greater and using all four eyebolts will void any warranty or service
claim.
7.
Use a 5/8" (1.5 cm) diameter rope, approximately 75-ft (20 m) long, as a tagline to steady the enclosure during lifting and
lowering operations. Attach the tagline to an eyebolt on the right side of the enclosure (looking at the front).
8.
Remove the pallet mounting hardware. (Requires 3/4” deep well socket.)
9.
Lift the enclosure. The pallet should drop off from its own weight.