![Veeder-Root TLS-450 Setup And Operation Download Page 111](http://html2.mh-extra.com/html/veeder-root/tls-450/tls-450_setup-and-operation_3793936111.webp)
TLS-450 Setup and Operation Screens Manual
100
Max Operating Level%
Enter the desired maximum operating height as percent of diameter.
Allowable selections: 50 to 99%. Default: 99%
AccuChart II Notes
1. If the TLS-450 is powered down during one of the Immediate or Periodic updates, or if a time/date
change is made at this time, the update will be missed. If this occurs during the final Periodic
update, or at the end of the calibration period for Immediate and Complete update selections, the
calibration will be attempted at the next date change. The update will be done with this
calibration, or the last generated calibration, or AccuChart II will generate warnings.
2. If you enter the Start Date values in a random order, the system will rearrange them in increasing
order. Empty Apply Date 1 through 4 fields will be grouped at the bottom of the set. This may
cause the entered values to move around.
3. If the calibration is in progress and the console clock is set back before the start of calibration, the
start of calibration will be moved back to the new time, and the 'Update Schedule' dates will all be
adjusted appropriately (including Periodic).
4. Touching the 'Start' button will bring up the confirmation dialog. If you click OK, the console will:
•
Set the start of calibration to the current date.
•
Set the Days Left To Calibration Completion equal to the number of days in calibration
period.
•
Clear all AccuChart II alarms and warnings.
5. While the calibration is running, the Start button changes to the 'Stop' button. If you touch the
Stop button, a confirmation dialog ('Are you sure you want to Stop the AccuChart II Calibration?')
will first be displayed before the calibration is stopped. Once you select OK in the confirmation
dialog, the Stop button changes to the 'Start' button.