8
In-Tank Leak Tests
Leak Test Duration
8-8
To set the test rate to 0.1 gph (0.38 lph), press CHANGE, then press ENTER to confirm your choice. The system
displays the following message:
Press STEP to continue.
Leak Test Duration
If necessary, press STEP until you see the following message:
To accept the displayed duration, press STEP. To set another test duration, press CHANGE. The maximum
duration is 6 hours. We recommend a minimum duration of two hours for 0.2 gph (0.76 lph) tests and three hours
for 0.1 gph tests.
Note: If you have Leak Test Early Stop enabled and the console determines that an in-tank leak test has passed
after the first two hours of the test, the test is completed, even though you had entered a Leak Test Duration of
more than 2 hours.
Enter the test duration in hours and press ENTER to confirm your choice:
Press STEP to continue.
Leak Test Early Stop
If necessary, press STEP until you see the following message:
Disabled is the default setting. When enabled this feature will prevent an In-Tank Leak Test from starting under the
following conditions:
1. Fuel level is less than Leak Min Periodic (0.2 gph test rate) or Leak Min Annual (0.1 gph test rate).
2. It is less than 8 hours from a delivery.
3. The product temperature is less than 0°F (-17.6°C) or more than +100°F (+37.4°C).
4. The fuel level is too low.
To accept the disabled condition, press STEP. To enable Leak Test Early Stop, press CHANGE and then ENTER
and the system displays:
Press STEP to continue.
TEST RATE: 0.10 GAL/HR
PRESS <STEP> TO CONTINUE
TEST DURATION: ALL TANK
DURATION: 02
DURATION: XX
PRESS <STEP> TO CONTINUE
TST EARLY STOP: ALL TANKS
DISABLED
TST EARLY STOP: ALL TANKS
ENABLED