YO20-0938-DI-001-00
3.3.1 How to hoist using crane
Never get under this machine
This machine may fall or topple if a forcible operation is performed or if the
equipment is not sufficiently maintained. Never get under this machine.
Use a crane or other cargo-handling equipment
Give instructions to lift and transfer this machine using a crane or other cargo-
handling equipment securely with the four eyebolts on the top of this machine
when unpacking or lifting it. Before using eyebolts, confirm that there are no
abnormalities. When hoist, make sure that hoist angle formed by the diagonal
lines of the hoisting attachments with 60 degrees or less.
Make sure to hoist this machine alone
When hoisting, remove the dedicated silencer. Hoisting with the dedicated
silencer mounted may damage the parts.
1
.
Prepare an appropriate hoisting attachment and check that the eyebolts are in normal condition (e.g.,
not loosened or damaged).
2
.
Hang the hoisting attachment on the pump’s eyebolts and the crane hook.
Figure 8:
Hoisting using Crane
3
.
Slowly operate the crane to hoist this machine until just before this machine leaves the ground.
4
.
Operate the crane again to hoist this machine until this machine leaves the ground.
5
.
After starting to hoist this machine, confirm that the belt sling and hoisting tool are in normal condition.
Confirm that the load is not inclined.
6
.
When unloading the machine, make sure to lower the crane slowly not to apply shock to or damage
the machine.
NOTES
Crane hook
Hoisting attachment (e.g. belt slings)
Eyebolt
Summary of Contents for MS120A
Page 2: ......
Page 10: ......
Page 14: ......
Page 47: ...33 YO20 0938 DI 001 00 Figure 16 I O block diagram for remote control wiring...
Page 65: ...51 YO20 0938 DI 001 00 7 2 External Dimensions Figure 17 External dimensions of MS120A MS120A...
Page 67: ...53 YO20 0938 DI 001 00...
Page 68: ...54 YO20 0938 DI 001 00...
Page 69: ...55 YO20 0938 DI 001 00...