Sunny Island 4500
Installation & Operating Instructions
BWRI45-13-EE0304
- 120 -
SMA Regelsysteme GmbH
“PARGEN“ (3+6)
Name
Description
“630_TavgLdSum“), that has to be exceeded, in order to
start the Ecopower CHP even in the case of charging states
between “631_PldLzMin” and “632_PldLzMax“.
634_PConsMax
0 … 10.000 W
Upper limit for the load power (cumulative power averaged
over all three phases within the time period of the parame-
ter), when the Ecopower CHP will already be started in the
case of a charging state of
“632_PldLzMax”.
635_PChargeMax
0 … 16.000 W
Setpoint for the charging power, that the Sunny Island ob-
tains from the Ecopower CHP.
636_PDump1
0 … 8.000 W
Power of Dumpload 1, that has to be connected to the relay
K1 of the Sunny Island during the operation with the eco-
power CHP. (“701_Man K1“ = Auto)
637_PDump2
0 … 8.000 W
Power of Dumpload 2, that has to be connected to the relay
K6 of the Sunny Island during the operation with the Eco-
power CHP. (“706_Man K6“ = Auto)
638_PBHKWMin
0 … 4.000 W
Minimum power of the Ecopower CHP
639_PBHKWMax
0 … 10.000 W
Maximum power of the Ecopower CHP
640_BHKW_ton
0 … 10.000 s
Minimum run-time of the Ecopower CHP
641_BHKW_toff
0 … 10.000 s
Minimum pause time of the Ecopower CHP
642_BHKW_tmax
0 … 20.000 s
Maximum run-time of the Ecopower CHP in mode 2 (fast
control)
0: No limitaition
644_PldOnLx
0 … 3300 W
Activation of the Ecopower CHP when the load at one phase
has been exceeded
0: No load-dependent activation
710 ... 715
Conditions for generator start: see Chapters 8.7 and 2.
Table 8.4:
Settings in menu “PARGEN“ (3+6)
Unlike all other special functions associated with the relays, the function to start the
generator via K1 depends on the battery state and may also depend on the day time
and can thus be defined by parameters 710 to 715, as shown in Chapter 8.7.