Commissioning and Acceptance Procedure
This chapter presents the recommended commissioning and acceptance procedure to
be performed following the installation of each EtherHaul ODU.
The commissioning and acceptance procedure verifies the correct installation and the
proper, safe, and robust operation of the EtherHaul RF link.
This chapter includes the following topics:
Installation Verification and Testing
EtherHaul Commissioning and Acceptance Form
5.1
Installation Verification and Testing
Inspect the following components and confirm their adherence to requirements that are
detailed in the accompanying checklist (
EtherHaul Commissioning and Acceptance Form
on page 58).
Hint:
Make copies of the
EtherHaul Commissioning and Acceptance Form
on page 58 and
use it as a comprehensive guide to RF link commissioning and acceptance.
5.1.1
Physical Installation Verification
This inspection verifies the physical installation of the ODU, in accordance with
For
detailed technical specifications
please refer to the datasheet.
Installing the EtherHaul 1200 on page 21.
Pole mount installation
ODU installation
Connectors’ sealing
Cables installation
Grounding
5.1.2
RF Link Test
This inspection verifies the RF link status, in accordance with
Performing Basic
Configuration Using the Web EMS
on page 36 and
Performing Basic Configuration using
the CLI
on page 48.
RF LED is green