Start-up
7
Observe the following when carrying out any work on the machine:
● Comply with the general safety instructions
● Comply with the applicable national and sector-specific regulations at the place of
installation
● When using the machine within the European Union, comply with the specifications laid
down in EN 50110‑1 regarding safe operation of electrical equipment.
See also
7.1
Checks to be carried out prior to commissioning
Once the system has been correctly installed, you should check the following prior to
commissioning:
Note
Checks to be carried out prior to commissioning
The following list of checks to be performed prior to commissioning does not claim to be
complete. It may be necessary to perform further checks and tests in accordance with the
specific situation on-site.
● The machine is undamaged.
● The machine has been correctly installed and aligned, the transmission elements are
correctly balanced and adjusted.
● All fixing screws, connection elements, and electrical connections have been tightened to
the specified tightening torques.
● The operating conditions match the data provided in accordance with the technical
documentation, such as degree of protection, ambient temperature, etc..
● Moving parts such as the coupling move freely.
● All touch protection measures for moving and live parts have been taken.
● For test operation or when commissioning without output element, carefully secure the
feather key using a suitable security element. When doing this, take into account the
balancing type of the motor.
SIMOTICS FD 1MM1
Operating Instructions 02/2019
95
Summary of Contents for SIMOTICS FD 1MM1 Series
Page 2: ...05 02 2019 16 03 V11 01 ...
Page 30: ...Description SIMOTICS FD 1MM1 30 Operating Instructions 02 2019 ...
Page 142: ...Maintenance 9 2 Corrective Maintenance SIMOTICS FD 1MM1 142 Operating Instructions 02 2019 ...
Page 166: ...Disposal 11 5 Disposal of components SIMOTICS FD 1MM1 166 Operating Instructions 02 2019 ...
Page 168: ...Service and Support SIMOTICS FD 1MM1 168 Operating Instructions 02 2019 ...
Page 172: ...Quality documents SIMOTICS FD 1MM1 172 Operating Instructions 02 2019 ...
Page 177: ......