8.5.1
Avoidance of condensation or formation of condensation within the machine
● If the controller does not do this automatically, switch on any anti-condensation heating
during stoppages. This will avoid the formation of condensation.
● Do not switch on the anti-condensation heating for at least two hours after the motor has
been switched off. This prevents damage to the winding insulation.
WARNING
Explosion hazard
If the anti-condensation heating is switched on directly after the machine is switched off, the
temperature class or the maximum surface temperature of the machine can be exceeded.
In an explosive atmosphere, there is a risk of an explosion. This can result in death, serious
injury or material damage.
● Only switch on the anti-condensation heating after the motor has been switched off.
Carefully comply with the data on the anti-condensation heating plate.
8.5.2
Avoidance of damage to roller bearings during stoppages
Extended stoppages at the identical or almost identical resting position of the roller bearings
can lead to damage such as brinelling or corrosion, for example.
● During stoppages, regularly start the machine up for a brief period once a month. As a
minimum, rotate the rotor several times.
If you have uncoupled the machine from the driven machine and secured the rotor with a
rotor shipping brace, then remove this before turning the rotor over or starting the machine
up.
Make sure that the resting position of the roller bearings after the rotor has been turned over
is different from what it previously had been. Use the fitted key or the coupling halves as
reference markers.
● During re-commissioning, refer to the information in the "Commissioning" section.
See also
8.5.3
Measurement of the insulation resistance after an extended stoppage
Measuring the insulation resistance and polarization index (PI) provides information on the
condition of the machine. It is therefore important to check the insulation resistance and the
polarization index at the following times:
● Before starting up a machine for the first time
● After an extended period in storage or downtime
● Within the scope of maintenance work
Operation
8.5 Stoppages
SIMOTICS FD 1MM1
Operating Instructions 02/2019
113
Summary of Contents for SIMOTICS FD 1MM1 Series
Page 2: ...05 02 2019 16 03 V11 01 ...
Page 30: ...Description SIMOTICS FD 1MM1 30 Operating Instructions 02 2019 ...
Page 142: ...Maintenance 9 2 Corrective Maintenance SIMOTICS FD 1MM1 142 Operating Instructions 02 2019 ...
Page 166: ...Disposal 11 5 Disposal of components SIMOTICS FD 1MM1 166 Operating Instructions 02 2019 ...
Page 168: ...Service and Support SIMOTICS FD 1MM1 168 Operating Instructions 02 2019 ...
Page 172: ...Quality documents SIMOTICS FD 1MM1 172 Operating Instructions 02 2019 ...
Page 177: ......