©2015 Siemens Protection Devices Limited
Chapter 7 Page 41 of 64
Section 4: Control Functions
4.1
User Defined Logic
4.1.1 Auto-Changeover Scheme Example
Figure 4-1 Example Use of Quick Logic
The MV installation illustrated above is fed from two incomers. To limit the substation fault level the busbar is run
with CB3 open. When a fault occurs on one of the incomers it is isolated by the circuit protection. To re-supply the
disconnected loads from the remaining incomer CB3 is closed.
If the line fault occurs on incomer 1 it must be confirmed that CB 1 has opened before CB3 can be closed. The
relay on incomer 1 confirms that a trip has been issued to CB1 (e.g. Binary Output 2), that CB 1 has opened (e.g.
Binary Input 1) and that no current flows in the circuit (e.g. 37-1 = Virtual 1):
Incomer 1 Relay is Configured:
CB1 Open auxiliary switch wired to B.I. 1
Trip output to CB1 = B.O. 2
OUTPUT CONFIG>OUTPUT MATRIX:
37-1
=
V1
OUTPUT CONFIG>OUTPUT MATRIX:
E1
=
BO3
CONTROL & LOGIC>QUICK LOGIC:
E1
=
O2.I1.V1
The output from Incomer 1 (BO3) relay is input to the relay on CB 3 (Binary Input 1). A panel switch may be used
to enable the On-Load Change-over scheme (Binary Input 2). Before Closing CB3 a check may be made that
there is no voltage on busbar 1 (27/59-1 = Virtual 1). CB 3 is closed from Binary Output 3.
CB3 Relay is Configured:
Panel switch (ON-Load Change-over Enabled) wired to B.I. 1
OUTPUT CONFIG>OUTPUT MATRIX:
27/59-1
=
V1
OUTPUT CONFIG>OUTPUT MATRIX:
E1
=
BO3
CONTROL & LOGIC>QUICK LOGIC:
E1
=
I1.I2.V1
If required a time delay can be added to the output using the CONTROL & LOGIC > QUICK LOGIC:
E1
Pickup Delay
setting
.
Summary of Contents for 7SR242 Duobias
Page 1: ...Answers for energy 7SR242 Duobias Transformer Protection Relay Reyrolle Protection Devices ...
Page 2: ...2 ...
Page 4: ...4 ...
Page 6: ...6 www siemens com energy ...
Page 318: ... 2015 Siemens Protection Devices Limited Chapter 7 Page 2 of 64 ...
Page 324: ... 2015 Siemens Protection Devices Limited Chapter 7 Page 8 of 64 ...
Page 358: ... 2015 Siemens Protection Devices Limited Chapter 7 Page 42 of 64 ...
Page 366: ... 2015 Siemens Protection Devices Limited Chapter 7 Page 50 of 64 ...
Page 380: ... 2015 Siemens Protection Devices Limited Chapter 7 Page 64 of 64 ...
Page 381: ......