49
Image
Action step
9. Select “No cascading”. In the case of
cascading: Add the settings for cascad-
ing. Take note of the instructions in Chap-
ter 8 of these installation instructions.
Example here: System with master system and
two subsidiary systems.
10. Confirm your input by clicking on “Next”.
11. Select the phases grid connection “1-Phase”.
12. If you are using a non-certified inverter and
hence have fitted a second power flow direc-
tion sensor, check the “measures consuption”
box, or the “measures generation” box in case
of the connection variant with a third power
flow direction sensor. If only certified inverters
are being used (neither power flow direction
sensor 2 or 3 fitted) the two checkboxes for
“Power Direction Flow Sensors” must be
cleared.
13. Confirm the input by clicking on “Next”.