5 Material required
5.1 Tools
The following insulated tools are required for problem-free installation of the SENEC.Home Li:
•
calibrated torque wrench, specified torque for M 6 - terminal screw: 5 Nm
•
slotted head screwdriver
•
cross-head screwdriver
•
5 mm Allen key
•
multimeter
5.2 Electrical
Data cables:
•
Cat.6 data cable with RJ45 plug connector for connecting to the PV inverter and/or power flow direction sensors
2/3
•
Cat.6 data cable with RJ45 plug connector for configuring the monitoring system
•
Cat.6 data cable with RJ45 plug connector for cascading multiple SENEC storage units and/or SENEC.Heat
Connection from the house wiring to the power flow direction sensor and SENEC.Home Li:
•
Cable, 5-core NYM, at least 2.5 mm
2
to a maximum of 6 mm
2
,
flexible with wire end ferrules
In the house wiring:
•
Residual current device, MCBs (3-pin B 16 A or 3-pin B 32 A on Econamic Grid)
•
Wiring set, customer-specific (check situation on site)
•
Recommended: overvoltage protection
Where connecting mains backup operation:
•
Cable, 3-core NYM, at least 2.5 mm
2
to a maximum of 6 mm
2
,
flexible with wire end ferrules
•
Insulation monitor
•
B 10 A miniature circuit breaker
When using the controllable outputs:
•
Cable, 3-core NYM, at least 2.5 mm
2
to a maximum of 6 mm
2
,
flexible with wire end ferrules
5.3 Other materials required
•
Conduit, fixings, cable ties
•
Laptop with LAN connection for configuring the monitoring system
•
Indelible pen for filling out identification plate