LED R&D Lab(VD)
49
□
Installation order
: FRAME →
CABINET
Frame Left
①
Separate Assy frame Vertical
Adjustment of flatness between walls
using Spacer-ETC
③
Adjust horizontals, verticals and fix the screw
Connection between upper and lower
cabinets using brackets
④
Install the cabinets of first level.
⑥
After installing 2nd level, fasten the
SIDE screws to fix modules.
⑤
Install horizontal shared side (Sliding)
Laser Level
Frame Right
Assy frame H
Assy frame V
Frame Right
Frame Left
②
Attach Assy frame H to Assy frame V
3. Frame kit Components
Summary of Contents for IFA Series
Page 1: ...LED R D Lab VD LED Display Installation Manual IWA IFA Series LH0 IWA W LH0 IFA VS Ver 3 3 ...
Page 54: ...LED R D Lab VD 53 4 Frame installation Precautions for Fastening the Screws ...
Page 130: ...LED R D Lab VD 129 8 S Box Installation and Connection S Box Grouping Support Frequency 1 2 ...
Page 131: ...LED R D Lab VD 130 8 S Box Installation and Connection S Box Grouping Support Frequency 2 2 ...
Page 200: ...Thank you ...
Page 213: ...LED R D Lab VD 212 Accessories configuration SNOW JMU Appendix 3 S BOX Accessory List ...