3-51
18
17
Connect the flexible cables and connector and fix the
cables with the Clamps.
Fix the Chassis with the 4 screws as shown in the figure.
SCREW
< Top View >
FLEXIBLE CABLE
CONNECTOR
CLAMP
FLEXIBLE CABLE
Perform the following operations after replacement.
1. DIP SW SETTING
2. BATTERY INSTALLATION
3. FIRMWARE INSTALLATION
4. SYSTEM PARAMETER INITIALIZE
5. IP ADDRESS SETTING
Start the machine with the Service Mode and set in the User Menu.
6. PUT PARAMETER
7. TIME AND DATE SETTING
Set the date and time in the [SERVICE MENU] > [SUB MENU] > [CLOCK].
*Set the [DATE] in order of the [Year/Month/Day].
8. FIRMWARE VERSION CONFIRMATION OF NETWORK CONTROLLER
9. SENSOR CHECK
It can be performed in the Sensor Check.
10. CROP MARK SENSOR ADJUSTMENT
11. CROP-CUT ADJUSTMENT
Necessary when the voltage is adjusted in the CROP MARK SENSOR ADJUSTMENT.
19
SCREW
Revised 4