RANS S-20 RAVEN
TEXT MANUAL
09/01/2013
03G-01
ROTAX 912ULS - THROTTLE CONTROL ASSEMBLY
(FINAL INSTALL OF ENGINE)
ASSEMBLY
•
The engine needs to be installed to the airframe.
•
Instrument Sub-panel must be installed
NOTE:
Adjustable Ferrule in Throttle Support Arm on Carburetor must be
remove and replaced with the Slip Fit Conduit Terminals supplied with
the Throttle Cable Assembly. Refer to Manufacturer's instructions.
1.
Refer to the parts catalog and select the required components for
assembly.
2.
Remove lock washer and retaining nut from Throttle Cable Assembly.
3.
Route Cables through center hole in Instrument Sub-panel. Secure with
lock washer and retaining nut.
4.
Install Rubber Grommets to lower set of 5/16" holes below Regulator
Rectifier on Firewall and route cables through. Refer back to
FIGURE
03A-02
.
5.
Route cables to each Carburetor leaving slack to allow for engine
movement and maintenance of carburetor.
NOTE: Throttle Control can be
pulled out slightly to allow trimming of Control Cable housings.
6.
After Choke Control is installed, cut provided Blue Line into segments and
secure with Plastic Ties to secure the Throttle and Choke Cable housings
together.
7.
Adjust to allow full throttle when control is pushed all the way in.
Synchronization of the carburetors is very important. There are videos on
the internet that show this procedure in detail.
NOTE: