Safety – Setting up and commissioning – Operation – Spare parts lists
Checklist – please tick
2021-03-22
41
32 Checklist – please tick
1.
Setting up the machine head
The two front latches on the machine head have been correctly closed:
O
The two rear latches on the machine head have been correctly closed:
O
Neither the magnetic belt nor magnetic mounts were damaged (visual inspection):
O
The machine head’s running properties were checked for ease of movement:
O
2.
Assembly of the particle boards (on the machine table)
The particle boards were screwed onto the machine table:
O
3.
Mounting the stop strip (MDF)
The MDF stop strip was mounted on the machine table:
O
4.
Connecting the extraction system
The suction hose on the extraction system was connected to the machine head:
O
5.
Supplying power to the machine
The extraction unit plug was connected to the local mains:
O
The orange machine power cable was plugged into the front of the extraction unit:
O
The extraction unit was set to automatic mode “RA”:
O
The main switch on the machine was switched on:
O
The function of the brakes and digital displays was checked:
O
6.
Setting up the cutting depth of the sawing units
The cutting depth of the sawing units was adjusted to the level of the particle boards:
O
7.
Adjusting the stop on the cross-cut axis
The stop on the cross-cut axis or zero point was set:
O
8.
Cutting off the MDF stop strip
The MDF stop strip was cut off:
O
9.
Locating the work plates
The work boards were located on the machine table:
O
The cutting depth of the sawing units was adjusted to the level of the work boards:
O
10.
Adjusting the milling depth for the milling cutter unit
The milling depth of the milling cutter unit was adjusted and a sample board was milled:
O
11.
Adjusting the machine stop for the milling cutter units
The machine stop was adjusted to match the milling cutter units:
O
The lock screw was retightened:
O