Safety – Setting up and commissioning – Operation – Spare parts lists
Start-up
2021-03-22
23
All three units have 2 long slots [
2
] in their mounting plates on the underside as well as integrated electric
connectors and an extraction opening (15.06).
Fig. 16:01
Fig. 16:02
Fig. 16:03
Locate the unit on a Y carriage plate (long slots on the bolts with V groove) [
1
]) and push against this plate;
the unit is automatically latched in place by the ratchet lever at the top [
2
].
The electric connection [
3
] and the extractor connection [
4
] are established in the process.
The power units can be inserted either at the front or rear as required.
To remove a unit from the carriage, lift the ratchet lever [
2
] – slightly tilt the unit to extend the electrical
connector [
3
] – and lift the unit off the bolt with V groove [
1
].
18 Start-up
For commissioning, the mains plug of the extraction system is connected to the mains and the
extraction system is set to R / A and diameter 35.
Subsequently, the mains plug of the machine is connected to the extraction system.
Turn on the main switch. Turn the red main switch clockwise until it automatically stops. The condition
is that the machine is connected to the mains.
The power units are switched on (left/OFF/right) with the power unit selector switch.
After completing the work, switch the power unit selector switch back to off.
To
shut-down
, switch off and lock the main switch and then unplug the mains plug.
Ratchet lever (
2
)
Electrical connector (
3
)
Extraction connection (
4
)
Positioning pin (
1
)