47
Changing SPs During Operation
Section 3-3
3-3
Changing SPs During Operation
Several channels are grouped together for control when gradient temperature
control is used. Therefore, switch banks and change the SP for all channels if
changing the SP during operation. Uniformity may be adversely affected if the
SP is not changed for all channels in the gradient temperature control groups.
The following example shows using bank switching to change SPs.
a.
Change the SP for bank 1 during control using bank 0.
b.
Switch to bank 1.
All SP for the group are refreshed when the bank is switched.
When the initial channel of a gradient group is switched, the bank of chan-
nels allocated for that group will be switched. For 2-PID control groups, the
bank can be switched for individual channels in a group.
CH1 SP
CH2 SP
CH1 PV
CH2 PV
CH1 and CH2 SP
CH1 and CH2 PV
When the SPs are changed at different times
When the SPs are changed at the same time
BANK
CH1 SP
CH2 SP
CH3 SP
0
100
100
100
←
Control using bank 0
1
150
150
150
←
Change bank 1 SP
BANK
CH1 SP
CH2 SP
CH3 SP
0
100
100
100
1
150
150
150
←
Switch to bank 1
Summary of Contents for EJ1G
Page 3: ...iv ...
Page 17: ...xviii ...
Page 21: ...xxii ...
Page 53: ...32 Unit Configuration Examples Section 2 4 ...
Page 69: ...48 Changing SPs During Operation Section 3 3 ...
Page 81: ...60 Other Functions Section 4 5 ...
Page 145: ...124 Other HFU Functions Section 5 7 ...
Page 167: ...146 Detailed Description of Services Section 6 4 ...
Page 229: ...208 Parameters That Can Be Allocated for Programless Communications Appendix ...
Page 237: ......